Formula and method
Cycle time is the sum of fill, pack, cooling, and mold-motion steps.
Inputs and units
Enter measured or specified values in the displayed units. Keep units consistent; results are rounded for practical planning. This first release uses the displayed engineering units rather than a unit-switcher.
Worked example
2.5 s fill + 5 s pack + 18 s cooling + 5 s mold motion = 30.5 s.
Time physical events, not setpoints
Define the cycle boundary first, then use observed or planned fill, pack/hold, cooling, opening, ejection, closing, and any automation time within that same boundary. A controller setting is not always the elapsed event time.
Use the total for the next decision
Send a credible cycle to Parts Per Hour or Cavity Count. Keep planned downtime and reject rate outside this arithmetic rather than hiding them in a shorter cycle.
Sanity check the cooling share
If cooling dominates the result, it is the first area to investigate—but only against ejection quality, gate freeze-off, dimensions, and warpage criteria.
Interpretation, assumptions, and limitations